Lifting Risk Assessment | Construction Lifting | Lifting hazards and control measures

 Lifting Risk Assessment | Construction Lifting | Lifting Hazards and Control Measures

Lifting Risk Assessment
Crane lifting
Risk Assessment of lifting Activity | Lifting hazards and Control Measures

Hazards

Control measures

 

· Uncertified /competent operator/rigger

 

 

 

 

 

 

 

 

 

 

· Uninspected Equipment / Tools

· Failure of equipment

· Crane tip-over

· Collapse of crane

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Falling objects & suspended loads

 

 

 

 

 

 

 

 

 

 

· Swinging the load

 

 

 

 

· Improper communication

 

 

 

 

 

· SIMOPS

 

 


Adverse Weather ( sand storm, high wind, heavy rain, fog)

- Obtain PTW system

- A pre-lift TBT to be carried out by the lift supervisor

- Lifting plan to be prepared prior to commencement of lifting operations.

- The lifting plan shall be clearly mentioned in the boom length, radius,   and load capacity.

- Operator must be competent with a valid license and have an approved 3rd party certificate

- Operator to conduct an inspection of crane (via Checklist) daily before use.

- Certified Rigger must be used at all times while performing lift using a crane.

 

- The crane/rigging equipment must have valid 3rd Party Certificates, inspected.

- The certificated and experienced rigger shall be assigned to the lifting for the Erection of equipment or material.

- Riggers& crane operators are to remain vigilant while moving the cranes within the Site working area

- The rigging supervisor should be competent in the unloading of heavy equipment

- The certificated and experienced rigger shall be assigned to Lifting/offload the lifting material.

- Outrigger shall be fully extended with suitable padding arrangement

- Crane must be set up on a level surface and sound outrigger pads to be used

- Do not extend the outrigger very close to the excavation edge

- Use safety lock pins in the D- shackles are used

- Use large radius shackles to avoid flattening and misshaping eyes of wire slings

- All the rigging gears shall be inspected by a competent person, and all defective rigging gear shall be removed from use

- Access to the cabin/Controls has been secured and restricted

- Activity must be supervised by a competent supervisor.

- Wind speed must be monitored and work should stop if wind speed reaches 10 m/s K/hr.

 

- Lifting area must be barricaded area

- Display safety signs (i.e. Lifting in progress)

- No one shall work below the suspended loads

- Secure all tools and materials to prevent them from falling on people below

- No Person enters the zone where a suspended load may fall, The lifting area shall be barricaded

- Loads do not exceed defined working load limits of plant and equipment

- The lifting operation will be stopped if the operation will found unsafe.

 

- Use tag lines for securing the load

- Auto alarm during swinging the boom

- The lifting area shall be barricaded.

- The Lifting, Shifting & offload activities shall be monitored by an experienced lifting Supervisor


- Proper communication between riggers & operators

- Competent rigger perform the given signals

- Radio communication with operator and riggers

 

 - No other activity performed in the nearby lifting area

- No one other contractor perform the activity during the lifting

 

- Stop the activity if it is bad weather (sand storm, high wind, heavy rain, fog)

- Reference to the local weather forecast, if there is heavy fog or strong wind, no offload activities will be allowed

Post a Comment

0 Comments