ACTIVITY

HAZARDS

CONTROL MEASURES

ABLE LAYING

·    Improper Manual Handling

·    Weight of cables

·    Lack of supervision

·    Improper  PPEs

·    Slip & Trip

·    Dust Particle

·    Hot weather

-          Obtain PTW before the start of the activity.                                                                                            

-          Conduct toolbox talk

-          Hand tools and equipment are placed at desired locations that do not interfere with the working area.                                                                                             

-          All the staff present shall be trained on safe manual handling techniques.                                                 

-          The activity shall be properly supervised by a competent person.                                                                        

-          The working area shall be barricaded and signposts shall be placed.                                                                               

-          All the mandatory PPEs shall be provided to staff.                                       

-          Watch your steps avoid to slipping & trip

-          Proper access with steps in the excavation area

-          Use a dust mask

-          Arrange a rest area, fresh drinking water, and frequent breaks shall be provided.

-          Get help sharing the load

Installation of Cable Tray

Sharpe edges

Falling objects

Weight of trays

Working at height

Improper manual handling

 

-          Skilled & experienced technicians and the worker shall be involved in the activity.

-          Barricaded falling objects area

-          Wear proper PPE as required

-          Wear proper hand gloves and avoid Sharpe's adages

-          Weight of cables trays share get help

-          Increase the number of workers during the installation of cable trays

-          Follow proper manual handling techniques for cable tray installation

-          Use a full-body harness belt at work at a height

-          Ensure proper scaffold platform with green tag inspection

-          Display safety signs for the area of the falling object

Installation of CT, VT, CVT & SA

·   Unskilled workers

·   Faulty tools

·   Work at height

·   Falling objects

 

-          Ensure skilled workers shall be involved in the activities

-          Ensure hand tools and equipment shall be inspected before the start of the work and shall be inspection tagged.                                                          

-          Anti-slip and cotton gloves shall be provided to workers along with other appropriate PPEs.    

-          Follow proper manual handling techniques for cable tray installation                                    

-          Use a full-body safety harness belt

-          Use inspected scaffold platform with a green tag

-          Barricaded  falling objects area

-          Tools should be attached with a tool tie

-          Display safety signs about falling objects

-          Work shall be under close supervision.      

Installation of  Conduit,

Cable Laying,

Lighting Fixtures,

and Lighting Tubes, Fans

and Exhaust Fans

 

·   Unskilled technicians & workers

·   Faulty tools

·   Work at a height

·   Falling objects

·   Slip & Trip

 

-          Obtain PTW system

-          Trained & experienced technicians & workers should be involved in these activities

-          Hand tools and equipment shall be inspected before the start of the work and shall be inspection tagged.                                                          

-          Only limited and relevant tools and equipment shall be present on site

-          A tool tie shall be used

-          Tagging of tools and equipment shall be done

-          Manual handling training shall be conducted for workers

-          Use a full-body safety harness belt

-          Use inspected scaffold platform with a green tag

-          Barricaded  falling objects area

-          Tools should be attached with a tool tie

-          Watch your steps to avoid slip & trip

-          Material & tools should be properly arranged

-          The material does not stack on the access

Installation of DBs  and Base Work

·    Working on live Electricity

·    Overloading power sockets

·    Spark

·    Electrocution

·    Using the wrong tools for the job

 

-          Ensure trained & experienced technicians are involved in this activity

-           No work shall be allowed at the energized system.                

-          Ensure before starting the work that the system is fully isolated and not energized.  

-          Proper isolation of the system shall be tested before the work.                        

-          Hand tools/gloves used shall be of respected voltage ratings with isolated handles and shall be fit for work.                                                                                     

-          Ensure the grounding was attached to the grounding point

-          Fire extinguishers available at the site

-          Double insulation is to be provided on the cables and proper cable management is to be ensured.

-          Ensure not overloaded power sockets

-          All the work shall be carried on under supervision.                                                                          

-          The area shall be properly barricaded before the start of work and signposts shall be placed.

-          Tools shall be inspected & tagged

Lightening Work

·   Working at a height

·   Loose materials and unfit hand tools

·   Falling  object

·   Slip, trip, and fall

·   Electrocution (Power Tools)

 

-          Conduct toolbox talks to highlight the hazards associated and controls that are implemented for it.

-          Hand tools and equipment shall be inspected before work and all the damaged tools shall be removed.                                                                         

-          Work at height training shall be provided to staff.              

-          Usage of safety harness shall be ensured and it shall be inspected before work to check for any damage/wear tear or incomplete part.                                                                

-          The platform provided shall have sufficient space present to work freely.                                               

-          The platform shall be properly tied or placed on the surface to avoid any movement.                                                             

-          All the tools and equipment shall be tied or placed securely on the platform to avoid a fall.                                                             

-          The platform shall contain a proper anchoring point or it shall be placed near the area where the anchoring point is present.                                                             

-          The platform shall not be placed on an uneven surface or the base plate or sole plate shall be placed in case it is placed.                                                                          

-          A proper ladder shall be provided for safe access and agreement.                                                                        

-          The working area shall be barricaded with a safety sign                                                          

-          The working platform shall be inspected on routine bases.                                                                                           

-          Usage of mandatory PPEs shall be ensured.                         

-          The working platform shall be placed closer to the working area or within reach of the person working.                                                                                           

-          Industrial Socket shall be used.

-          Proper earthling of DB.

-          In-house training of all the staff on safe manual handling

-          In-house training of all the staff on working at height.

-          Usage of tool lanyard with pulley.

-          The safety harness shall be inspected and tagged (Red/Green) and it shall contain double D-hooks.

-          All electrical connections/ cables/ sockets shall be properly inspected before the execution of work.

-          Surface shall be done even before placing the platform

Earthling Grounding

Earthling/ Mesh Laying

 

·   Uninspected tools & equipment

·   Overloading

·   Wrong lifting tools and tackles

·   Collapse of load

·   Improper Lifting preparations

·   Work at height

·   Falling objects 

-          Hand tools and equipment shall be inspected before the start of the work and shall be inspected.                                                          

-          Trained & skilled workers shall be used for the activity

-          PPEs provide as per the required standards

-          Do not overload the during a lifting activity

-          Choose the correct tools & equipment

-          Use two tag lines for securing the load

-          Proper communication between riggers & operators

-          Stop the activity if it is bad weather (sand storm, high wind, heavy rain, fog)

-          PPEs must be ensured (Harness, shoes, helmets).                     

-          Ensure proper placement of tools and other equipment.                                                   

-          Brief working procedure.                            

-          Use properly inspected Manual/ Power tools and check tools before use.                                          

-          Use a full-body safety harness

-          Choose the proper anchor point

-          Tools & equipment are attached with a tool tie

-          Barricaded area 