HSE Inspection & Audit Procedure | Inspection Procedure | Audit Procedure
![]() |
Audit & inspection |
HSE
INSPECTION & HSE AUDIT
Different kinds of HSE
inspections and audits shall be conducted for this project, the inspections and
audits are summarized as follows:
·
HSE Walkthroughs
·
Client or its delegate's HSE inspection
·
Company corporate HSE inspection
·
Project management site tour.
·
Project-specific HSE inspection (equipment safety inspection,
scaffold inspection, electricity inspection, adverse weather impact inspection,
etc.)
The Company Project management
department shall conduct planned HSE inspections, the inspections may include
but are not limited to the following.
·
HSE personnel daily regular site HSE inspection
·
Weekly walkthroughs with project Management
·
Equipment prequalification inspection and quarterly safety
inspection
·
Specific HSE inspection, for example, Electrical inspection,
scaffold inspection, lifting gear inspection, etc.
All HSE inspection
observations shall be corrected properly timely, and the observations shall be
logged on a register. A safety analysis shall be conducted for the registered
HSE observations to identify the current main HSE concerns, based on the
observation analysis result, the specific safety control measures shall be
taken accordingly. All HSE observations shall be documented and maintained
properly by the HSE department.
HSE meetings between the company
and its Subcontractors shall be organized as necessary while implementing the
project monitoring program, for instance: the HSE audit and inspection kick-off
meeting and close-out meeting, etc.
The project HSE team,
including subcontractors, will carry out daily site inspections covering project
site active and support areas. Inspections must cover all site aspects
including but not limited to access and egress, emergency arrangements, ongoing
activities, working platforms, environmental aspects, interface with public
and/or other contractors, welfare facilities, stores and laydown areas, tools
and equipment, electrical installations, permits to work, operatives
qualification and competencies, displayed notices, use of PPE, etc.
HSE inspection findings shall
be communicated on the spot with the concerned parties and corrective actions
shall be taken immediately whenever possible. When immediate corrective action
is not possible, the inspector shall evaluate the risk and act upon it. For low-risk
findings, the inspector shall agree with the concerned party on a reasonable
timeframe to take the required actions and shall monitor the progress to ensure
compliance with the agreement and follow up when and where required. Repetitive
low-risk findings shall be escalated and treated as medium risks. When a medium
risk is observed and immediate corrective action is not possible, measures
shall be taken to reduce the risk or the consequences as low as reasonably
practical until corrective actions are taken. If the corrective actions can’t
be taken within the same working shift, the inspector has to report the
situation to the project HSE manager who shall evaluate the risk and decide
whether the work may proceed or not. When a major risk that presents an
imminent danger is observed, work shall stop immediately, people shall be
removed from the danger zone, and appropriate measures shall be taken on the
spot to avoid other people from entering the danger zone until the required
measures are taken, the area is safe and the work process doesn’t present a risk
to people, properties and the environment.
Medium and high-risk
Inspections’ findings shall be discussed during the HSE meetings and toolbox
talks to reduce the chance of its reoccurrence.
Inspections’ findings shall be
recorded using the “HSE Inspection Report” and records shall be maintained by
the HSE department.
In addition to the general HSE
inspections, specific inspections shall be conducted regularly with items or
discipline targets including, but not limited to, equipment, tools, lifting
gears, personal fall arrest systems, electrical connections and installations,
ladders, scaffolds, excavation trenches, etc.
The project Management team
shall, regularly, conduct site HSE walkthroughs where they target one focus
area /zone and cover all HSE aspects in it. The walkthrough shall include
communication with the teams working in the area, advising them on safe working
practices, and getting their feedback.
This walkthrough must be
recorded including the date and time, participants, areas/zones covered,
findings, feedback, corrective actions, preventive actions, responsible persons,
and close-out timeframes. The project HSE Manager has the responsibility of
distribution and maintenance of the records as well as following up with all
parties who are required to take corrective and/or preventive actions.
The project will be subject to
internal and external audits. Internal audits will be conducted by the HSE
department where the project documentation as well as the project sites will be
thoroughly audited to ensure the project compliance with the corporate HSE
management system.
External audits will be
conducted by a third party as part of the OHSAS 18001:2007 certification
process.
Audits reported will be sent
to the project management team who shall take the necessary actions to close
out all non-conformances within the given timelines.
0 Comments